Sports Complex - Futsal/Pickleball

This project will enhance the Physical Education program offerings by constructing a multi-use basketball/futsal court with an additional eight pickleball courts on the southeast portion of campus.

View Project Updates

 

A community and campus asset, the courts will be open to students and the surrounding EVC community. There will be associated site work necessary to provide ADA access to the courts. Viewing patios may be included in the construction with a new patio at MS3 and adjacent to the tennis courts for public use during games.

Construction is projected for completion in August 2021.



Project Updates

December 2021

Past Month’s Accomplishments: The project is complete.

Next Month’s Milestones: N/A


November 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Project closeout will be finalized.


October 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Project closeout will be finalized.


September 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Punch list items and architectural features will be completed, followed by project closeout finalization.

7EB0304A-65AD-4E8F-82F7-5C86B5DDCBE4.jpeg
20DFE661-1330-45C7-8987-10533A8E1227.jpeg

August 2021

Past Month’s Accomplishments: Concrete, landscape planting and irrigation, lighting, fencing, and court surface were all completed.

Next Month’s Milestones: Punch list items and architectural features will be completed.

EB531A18-E5CB-4DFE-9308-6D9514A69B19.jpeg
D094B74C-8C22-459A-8E12-3DFB83AFB3E2.jpeg

July 2021

Past Month’s Accomplishments: Concrete flatwork, irrigation, lighting, fencing, seating wall and viewing patio were all completed.

Next Month’s Milestones: Court surface, sports equipment, lighting, landscaping, and architectural features will be completed. Substantial completion is scheduled for 8/27/21.

F1B7D074-DBC1-42C6-9395-C187D42E0466.jpeg
354447F8-21CA-49D1-9DFC-398D99FFBCF5.jpeg

June 2021

Past Month’s Accomplishments: Installation of asphalt paving, masonry wall, concrete flatwork and irrigation are underway.

Next Month’s Milestones: Concrete flatwork, lighting, fencing, seating wall and viewing patio will be completed.

Picture2.png
Picture3.png

May 2021

Past Month’s Accomplishments: Underground utilities, masonry, concrete, and structural steel were completed.

Next Month’s Milestones: Concrete and asphalt paving and the viewing patio will be completed.

5E9C39EB-A596-4A8E-9C5F-61016B4E07A7.jpeg
E1DBC95A-CD5B-4B72-8800-AE6614418200.jpeg

April 2021

Past Month’s Accomplishments: The contractor completed rough grading of the site and started work on underground utilities.

Next Month’s Milestones: Installation of the utility infrastructure will continue. It is anticipated that work on the foundation and structural steel will begin.

Construction Updates: Current and upcoming work includes installation of shade structures, bleacher slab concrete pouring, installation of wing walls, continued installation of shade structures, continued irrigation installation and drainage, digging foundation for viewing patio, and digging for dry-stack footing.

Construction Updates2.jpg
Construction Updates1.jpg

March 2021

Past Month’s Accomplishments: Started construction. Completed rough grade. Commenced underground utilities.

Next Month’s Milestones: Continue utility installation. Foundations to commence.


February 2021

Past Month’s Accomplishments: Started construction.

Next Month’s Milestones: Complete rough grade. Commence underground utilities.

Sports Complex.jpg

January 2021

Past Month’s Accomplishments: Attained DSA Approval Bid Award to Lewis and Tibbets. Notice to proceed issued.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.

scfp-01-nov.jpg
scfp-02-nov.jpg

December 2020

Past Month’s Accomplishments: Attained DSA approval bid award to Lewis and Tibbets, Inc.

  • CEQA: A Notice of Determination (NOD) was filed with the County Clerk. The County Clerk will post the NOD for 30 days.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.

  • CEQA: The NOD statute of limitations to challenge the District’s project approval on CEQA adequacy of the mitigated negative declaration closes.


November 2020

Past Month’s Accomplishments: Attained DSA Approval Bid Award to Lewis and Tibbets, Inc.

  • CEQA: Notice of Determination (NOD) was filed with the County Clerk after the after the Sports Complex project construction bid was awarded by the Board. The County Clerk will post the NOD for 30 days.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.

  • CEQA: The NOD will be posted for 30 days to allow for statute of limitations to challenge the District’s project approval on CEQA adequacy of the Mitigated Negative Declaration.


October 2020

Past Month’s Accomplishments: Attained Division of the State Architect (DSA) approval.

  • CEQA: At the October Board of Trustees meeting the California Environmental Quality Act (CEQA) study and recommendations were approved.

Next Month’s Milestones: An award will be made by the Board of Trustees to the recommended contractor at the next board meeting. The Bond Team will issue a construction contract and prepare the site for construction.

  • CEQA: A Notice of Determination (NOD) will be filed with the county clerk after the Sports Complex project construction bid is awarded by the Board. The county clerk will post the NOD for 30 days to allow for statute of limitations to challenge the District’s project approval on California Environmental Quality Act (CEQA) adequacy of the Mitigated Negative Declaration.


September 2020

Past Month’s Accomplishments: Design has been under Division of the State Architect (DSA) review since June. It is anticipated that DSA approval will be received in October. The team reviewed project budget and estimates to ensure proper funding.

  • CEQA: Advertised the Initial Study/Mitigated Negative Declaration  for public comment  from mid-August to mid-September 2020. No public comments were received.  Developed and finalized the Mitigated Monitoring Reporting Program.

Next Month’s Milestones: Finalize DSA review and construction budget. Advertise for construction bid.

  • CEQA: Submit the Initial Study/Mitigated Negative Declaration and Mitigated Monitoring and Reporting Program for review by the Board of Trustees at the October Board Meeting. A closed Board session will take place for final review.


Project Updates

November 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Project closeout will be finalized.


October 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Project closeout will be finalized.


September 2021

Past Month’s Accomplishments: Punch list items were addressed.

Next Month’s Milestones: Punch list items and architectural features will be completed, followed by project closeout finalization.


August 2021

Past Month’s Accomplishments: Concrete, landscape planting and irrigation, lighting, fencing, and court surface were all completed.

Next Month’s Milestones: Punch list items and architectural features will be completed.


July 2021

Past Month’s Accomplishments: Concrete flatwork, irrigation, lighting, fencing, seating wall and viewing patio were all completed.

Next Month’s Milestones: Court surface, sports equipment, lighting, landscaping, and architectural features will be completed. Substantial completion is scheduled for 8/27/21.


June 2021

Past Month’s Accomplishments: Installation of asphalt paving, masonry wall, concrete flatwork and irrigation are underway.

Next Month’s Milestones: Concrete flatwork, lighting, fencing, seating wall and viewing patio will be completed.


May 2021

Past Month’s Accomplishments: Underground utilities, masonry, concrete, and structural steel were completed.

Next Month’s Milestones: Concrete and asphalt paving and the viewing patio will be completed.


April 2021

Past Month’s Accomplishments: The contractor completed rough grading of the site and started work on underground utilities.

Next Month’s Milestones: Installation of the utility infrastructure will continue. It is anticipated that work on the foundation and structural steel will begin.

Construction Updates: Current and upcoming work includes installation of shade structures, bleacher slab concrete pouring, installation of wing walls, continued installation of shade structures, continued irrigation installation and drainage, digging foundation for viewing patio, and digging for dry-stack footing.


March 2021

Past Month’s Accomplishments: Started construction. Completed rough grade. Commenced underground utilities.

Next Month’s Milestones: Continue utility installation. Foundations to commence.


February 2021

Past Month’s Accomplishments: Started construction.

Next Month’s Milestones: Complete rough grade. Commence underground utilities.


January 2021

Past Month’s Accomplishments: Attained DSA Approval Bid Award to Lewis and Tibbets. Notice to proceed issued.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.


December 2020

Past Month’s Accomplishments: Attained DSA approval bid award to Lewis and Tibbets, Inc.

  • CEQA: A Notice of Determination (NOD) was filed with the County Clerk. The County Clerk will post the NOD for 30 days.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.

  • CEQA: The NOD statute of limitations to challenge the District’s project approval on CEQA adequacy of the mitigated negative declaration closes.


November 2020

Past Month’s Accomplishments: Attained DSA Approval Bid Award to Lewis and Tibbets, Inc.

  • CEQA: Notice of Determination (NOD) was filed with the County Clerk after the after the Sports Complex project construction bid was awarded by the Board. The County Clerk will post the NOD for 30 days.

Next Month’s Milestones: Board approval of construction contract. Contractor mobilization.

  • CEQA: The NOD will be posted for 30 days to allow for statute of limitations to challenge the District’s project approval on CEQA adequacy of the Mitigated Negative Declaration.


October 2020

Past Month’s Accomplishments: Attained Division of the State Architect (DSA) approval.

  • CEQA: At the October Board of Trustees meeting the California Environmental Quality Act (CEQA) study and recommendations were approved.

Next Month’s Milestones: An award will be made by the Board of Trustees to the recommended contractor at the next board meeting. The Bond Team will issue a construction contract and prepare the site for construction.

  • CEQA: A Notice of Determination (NOD) will be filed with the county clerk after the Sports Complex project construction bid is awarded by the Board. The county clerk will post the NOD for 30 days to allow for statute of limitations to challenge the District’s project approval on California Environmental Quality Act (CEQA) adequacy of the Mitigated Negative Declaration.


September 2020

Past Month’s Accomplishments: Design has been under Division of the State Architect (DSA) review since June. It is anticipated that DSA approval will be received in October. The team reviewed project budget and estimates to ensure proper funding.

  • CEQA: Advertised the Initial Study/Mitigated Negative Declaration  for public comment  from mid-August to mid-September 2020. No public comments were received.  Developed and finalized the Mitigated Monitoring Reporting Program.

Next Month’s Milestones: Finalize DSA review and construction budget. Advertise for construction bid.

  • CEQA: Submit the Initial Study/Mitigated Negative Declaration and Mitigated Monitoring and Reporting Program for review by the Board of Trustees at the October Board Meeting. A closed Board session will take place for final review.