MS3 Canopy

To enhance protection from the rain, a new canopy is being added to the Northwest end of the MS3 building.

View Project Updates

 

Project Updates

July 2022

Past Month’s Accomplishments: Project close out was completed.

Next Month’s Milestones: Project is complete.


June 2022

Past Month’s Accomplishments: Punch list and DSA closeout process is in progress.

Next Month’s Milestones: Building sign will be refabricated and its installation will be scheduled. The final stages of the closeout process will begin.


April 2022

Past Month’s Accomplishments: No change.

Next Month’s Milestones: Installation of building identification signage will be completed.


March 2022

Past Month’s Accomplishments: Installation of canopy was completed. Installation of pathway bollards was completed.

Next Month’s Milestones: Building identification signage to be installed.


February 2022

Past Month’s Accomplishments: Installation of the canopy was completed.

Next Month’s Milestones: Building identification signage will be installed along with pathway bollards.


January 2022

Past Month’s Accomplishments: Installation of canopy shade material was completed.

Next Month’s Milestones: Lighting and gutters will be installed.


December 2021

Past Month’s Accomplishments: Welding of structural steel and restoration of the courtyard are complete.

Next Month’s Milestones: Installation of canopy glazing, lighting, and finishes will be completed.


November 2021

Past Month’s Accomplishments: Steel erection was completed. Welding is in progress.

Next Month’s Milestones: Installation of canopy glazing and finishes will be completed.


October 2021

Past Month’s Accomplishments: Footings were poured and curing for the steel installation was completed.

Next Month’s Milestones: Light poles will be installed along Valle del Lago.


September 2021

Past Month’s Accomplishments: Rebar was put in place for footing construction.

Next Month’s Milestones: Concrete pouring and anchor bolt installation will begin. Submission of deferred submittals will be completed.

IMG_2021_09_16_07_16_41_412.jpg
IMG_2021_09_16_07_18_08_204.jpg

August 2021

Past Month’s Accomplishments: Site mobilization was completed. Materials and submittal approvals are expected.

Next Month’s Milestones: Site grubbing and concrete work will be completed.

IMG_2021_08_31_07_57_05_654.jpg
IMG_2021_08_31_07_55_18_934.jpg

July 2021

Past Month’s Accomplishments: JKL provided construction kick-off documents and has started early submittals.

Next Month’s Milestones: Mobilization to site and start of civil scope.


June 2021

Past Month’s Accomplishments: Four bids were received. JKL Construction provided a low bid.

Next Month’s Milestones: An award is expected at July 2021 Board meeting. The construction kickoff is anticipated to occur in mid-July.

Picture47.png

May 2021

Past Month’s Accomplishments: Re-release of solicitation for contractor through public bid. Contract to the July 2021 Board meeting was sent for approval.

Next Month’s Milestones: Receipt of bids and preparation for Board award.


April 2021

Past Month’s Accomplishments: Public bid opportunity.

Next Month’s Milestones: Re-release of solicitation for a contractor through public bid. Contract to the July 2021 Board meeting will be sent for approval.


March 2021

Past Month’s Accomplishments: Outreach for bidders.

Next Month’s Milestones: Procurement of contractor through public bid. Contract to the May 2021 Board meeting for approval.


February 2021

Past Month’s Accomplishments: Approval from DSA.

Next Month’s Milestones: The project will be issued for bidding.

ms3-03-nov.jpg

January 2021

Past Month’s Accomplishments: Completed design for DSA backcheck

Next Month’s Milestones: Approval from DSA


December 2020

Past Month’s Accomplishments: Awaiting DSA review comments.

Next Month’s Milestones: Approval of signage package and DSA approval.


November 2020

Past Month’s Accomplishments: Awaiting DSA review comments.

Next Month’s Milestones: Evaluate building identification signage on canopy. Await DSA review comments.


October 2020

Past Month’s Accomplishments: Additional updates to the architectural drawings were incorporated per Division of the State Architect (DSA) comments.

Next Month’s Milestones: Receive Division of the State Architect (DSA) approval.


September 2020

Past Month’s Accomplishments: Updated construction estimates.

Next Month’s Milestones: Anticipated approval from Division of the State Architect (DSA).